Project Objective

With a urgent requirement to expand their production facility to meet their increased demand, our client, a specialist in pharmaceutical production and distribution, requested our recommendations.

They required an ISO 7 multiroom cleanroom facility with temperature control, specialist two room close control system, filtration, pressure monitoring and extraction for Wash Room.

The Process

We were appointed to help design and build an ISO 7 cleanroom facility to enable our client to meet their growing demands by creating a larger space for their production.

After extensive surveying of the empty warehouse space, we worked with the client over a number of months to finalise the layout/design that would ensure an efficient transition of their product and personnel in each stage of production. Particular attention was given to the layout of the facility and the size of each area to create the most efficient use of space and close control in two rooms only.

Results

Working closely with the client and after successful installation of the new ISO 7 cleanroom facility, our client has benefited from:-

  • The ability to produce larger amounts of their products
  • Designated rooms with close control
  • Designated wash room area for product container cleaning
  • Reduced costs as outsourcing has been eliminated
  • The capability to grow their business and meet the growing demands of the industry

A more in-depth look at this project is available in our blog: The challenges and innovations of designing and building a cleanroom facility

Scope of works

  • Walls
  • Wall cladding
  • Ceiling
  • Floor
  • Electrical
  • Lighting
  • Mains Power
  • Air Conditioning
  • Filtration
  • Humidity Control
  • Pressure monitoring
  • Glazing
  • Commissioning /Validation
  • CDM – Principal Contractor/Designer

Project Value – £294,000.00

“So, a huge congratulations and thank you from me, for the hard work and professionalism shown throughout the project.”

Greig Downie
Complete Compliance Solutions

Our Case Studies…

Paragraf, Somersham - ISO 6 & ISO 8 Cleanrooms

They required a GMP Grade B, C and D cleanroom facility with temperature control, filtration, pressure monitoring and ventilation.

Read case study

Xeal Pharma, ISO 7 Multiroom Cleanroom, Birmingham

With a urgent requirement to expand their production facility to meet their increased demand, our client, a specialist in pharmaceutical production and distribution, requested our recommendations.

Read case study

Blink Medical / Corsa Medical, ISO 7 Cleanrooms, Solihull

We were appointed to help design and build an ISO 7 cleanroom facility to enable our client to manufacture products in house and create a quality control office to maintain their high quality standards.

Read case study

Exstent Ltd, ISO 5, ISO 6 & ISO 7 cleanroom, Tewkesbury

With a urgent requirement to expand their production facility to meet their increased demand, our client, a specialist in personalised external aortic root support, requested our recommendations.

Read case study

Automotive, ISO 7 Cleanroom, Bolton

We were appointed to design and build a cleanroom facility to enable our client to continue expanding their business and meet their growing demands by utilising their existing space more efficiently.

Read case study

Aerospace, ISO 7 and ISO 8 Cleanroom, Somerset

We were appointed to design and build a cleanroom facility along with quality review space to enable our client to continue expanding their business and meet their growing demands by utilising their existing space more efficiently.

Read case study

Testcard, ISO 8 Cleanroom, Scarborough

With an urgent requirement to expand their production facility to meet their increased demand, our client, a specialist in at-home medical testing providing immediate test results at a low cost, requested our recommendations.

Read case study

Andel Plastics Ltd, ISO 8 Cleanroom, Birmingham

With an urgent requirement to expand their production facility to meet their increased demand, our client, a specialist injection moulding and toolmaking company, requested our recommendations.

Read case study

Microsystems UK, ISO 7 Cleanroom, Warrington

Airology were appointed to design and build a cleanroom facility to enable our client to expand their business and meet their growing demands by creating a larger space for production and administration within their new premises.

Read case study

Trackwise, ISO 7 Cleanroom, Tewkesbury

We were appointed to design and build a cleanroom facility to enable our client to expand their business and meet their growing demands by creating a larger space for production.

Read case study

Always Pure Organics, ISO 8 Cleanroom, Manchester

We were appointed to help design and build an ISO 8 cleanroom facility to enable our client to manufacture products in house to maintain their high quality standards.

Read case study

Sheffield University, ISO 7 Cleanroom, Sheffield

Sheffield University required an ISO 7 cleanroom facility with temperature control and filtration to prevent contamination during testing, ensure high quality standards and efficient data analysis.

Read case study

Aerospace, Cleanroom Design, Somerset 2015

The client required an existing manufacturing space to be converted in an ISO 8 cleanroom facility with temperature control, filtration and pressure monitoring.

Read case study

Aerospace, ISO 7 and ISO 8 Cleanrooms, Somerset 2020

We were appointed to design and build a cleanroom facility to enable our client to continue expanding their business and meet their growing demands by utilising their existing space more efficiently.

Read case study

Spa Medica – Worcester

Airology Systems were appointed to design and install the air handling systems for theatre and treatment rooms at Spa Medica Eye Hospital in Worcester.

Read case study